Chapter 7 · ICSE Class 7 Mathematics

Unitary Method (including Time and Work)

Learn to find the value of one unit first, then scale it up or down to solve everyday problems — including how long a job takes.

🧮 Chapter 7

Using the unitary method to find how many days 10 workers take to finish a job If 5 workers finish a job in 8 days, the unitary method finds that 1 worker would take 40 days, so 10 workers take 4 days 5 workers 8 days ÷5→ 1 worker 40 days ÷10→ 10 workers 4 days More workers → fewer days (inverse relationship)
7.1

Finding the Value of One Unit

The unitary method means finding the value of a single unit first, then multiplying to find the value of any number of units. This works for cost, distance, speed, and many other real-world situations.

1

If 5 pens cost ₹75, what is the cost of 8 pens?

1 pen = ₹75 ÷ 5 = ₹15, so 8 pens = ₹15 × 8 = ₹120

2

A car travels 240 km in 4 hours. How far does it travel in 7 hours at the same speed?

1 hour = 240 ÷ 4 = 60 km, so 7 hours = 60 × 7 = 420 km

7.2

Time and Work

If a person can complete a job in a certain number of days, they complete 1/(number of days) of the job each day. Adding up daily work rates helps solve problems about people working together.

1

If a worker can finish a wall in 10 days, what fraction of the wall is completed in 1 day?

1/10 of the wall

2

If a worker completes 1/10 of a job in a day, how many days to complete 3/5 of the job?

3/5 ÷ 1/10 = 3/5 × 10 = 6 days

Practice

Exercises

1. If 6 notebooks cost ₹90, what is the cost of 10 notebooks?

2. A machine produces 150 toys in 5 hours. How many toys in 8 hours?

3. A worker can complete a job in 12 days. What fraction is completed in 1 day?

4. If a tap fills 1/8 of a tank in an hour, how many hours to fill the whole tank?

5. If 4 workers can build a wall in 15 days, how many days would it take 1 worker alone (assuming the same work rate)?